Step 3: sprint planning (requirements)

16 Jan 2025
3 min read
<span id=Step 3: sprint planning (requirements)">

If you’ve followed the first 2 steps in the ‘How to Implement Scrum in 10 Easy Steps’ series, you should now have your product backlog in order and have estimated its size using Fibonacci points.

The next step to implement Scrum – Step #3 – is Sprint Requirements.

Sprint Requirements Workshop

Call a Sprint Requirements meeting. Make sure the meeting is attended by the whole team. Include all roles. Business Analysts if you have them. Testers if you have them. ALL Developers on the Scrum team for the product. And very importantly the Product Owner.

The first thing you must do (in your first Sprint Planning meeting) is decide on your Sprint duration. This decision should be taken as a team.

Decide Your Sprint Duration

This is an important decision in the Scrum implementation process. Scrum suggests 30 days. It might be right. But this is one point that seems to be widely adapted by agile teams practicing Scrum.

The optimum Sprint duration depends on many factors. Something I read recently suggested that a development team’s ‘cycle time’ is a direct reflection of the maturity of their processes. I think I would agree with that statement.

A team with immature processes will find the intensity of Scrum and the overhead of Sprint Planning, Testing, Deployment and Review quite onerous for a short Sprint cycle. Whereas teams with very mature processes (for example automated testing, automated deployment, and teams who’ve become very quick at Sprint Planning), a short cycle might be very comfortable.

I’d suggest the range is between 1 week and 1 month. 1 week is probably the shortest that will ever be practical, although if you really master agile practices, why not ship each new feature when it’s ready? (if that’s appropriate for the product). 1 month should certainly be the longest.

For fast-moving products or markets, such as web-based products – where there is central deployment and no rollout or user training – 1 month seems like a lifetime! Personally I like 2 week Sprints for fast moving products.

Mike Cohn is one of the key exponents of agile development. See here for Mike’s article giving further advice about how to select the optimum iteration length.

Keep Sprint Duration Consistent

Whatever Sprint duration you choose to go for, my advice is to keep it consistent.

This, in fact, is more important than the length itself. Because it’s this consistency that allows you to get into a rythm. It’s this consistency that makes your process very repeatable. And therefore helps you to get into your stride as a team. And it’s this consistency that allows you to start understanding how many Product Backlog points you can typically do in a Sprint.

Once you’ve decided, you can now set up a Sprint Planning Workshop as a recurring appointment before every Sprint.

Select Target Backlog for Sprint

Now you’ve decided on your Sprint duration. Next you must decide on the goal for the Sprint…

Looking at the top section of the Product Backlog, what would seem to be a reasonable goal to set for the Sprint? Can you express an objective that sums up the goal for the next Sprint, or at least pick a section of items/features from the top of the Product Backlog that the team thinks can be achieved in the Sprint duration?

Select your target backlog for the Sprint. Make this decision as a team.

Include a bit more than you think can be achieved. It’s important to prepare more items during planning in case the team finishes early. These items can be clearly identified as stretch tasks and the Product Owner should not expect them to be completed. These are the things you will only do if the Sprint goes better than you expected.

In future Sprints, you will be able to use your Scrum team’s previous Velocity to help with this decision. Velocity is the number of Product Backlog Points delivered in a Sprint. This tends to fluctuate wildly early on when adopting Scrum. But it will settle down as the team get into a rythm, and in future provide you with a reasonable norm to base your target backlog on.

Clarify Sprint Requirements

Take each item on the Product Backlog. It’s important to go through them methodically, one item at a time…

The Product Owner presents each item and explains how he/she sees it working from a functional perspective.

The whole team discusses the item in detail. The whole team asks questions about the feature in order to establish what it should do and how it should work.

The outcomes of this discussion should be captured on a whiteboard or flipchart, or someone could write notes on a laptop as the discussion progresses. Interactive or printable whiteboards are ideal for this process.

You can use whatever form of writing requirements you want to. But the important principle in implementing Scrum, and in any agile development methodology, is that you write requirements feature by feature, just before they are developed.

Write requirements in a way that is lightweight and visual. Agile requirements should be barely sufficient. The fact the features will be developed and tested within the next few weeks, and by the team that were present, makes this possible.

Consider writing ‘User Stories’, a concept from XP (Extreme Programming). It’s beyond the scope of this article to explain user stories in any detail. But the basic concept is to write features using this construct:

As a [type of user], I want to [do whatever], so I can [achieve what goal].

The story can be backed up by a sketch of the UI, a wireframe or visuals. Annotate the sketch to describe the functionality. Backed it up with statements about how it will be confirmed (or tested). This will help to identify scenarios up front, before it’s developed.

For more information about user stories, Mike Cohn has written a book, User Stories Applied.